Why Workforce Planning Can't Wait Until Construction Starts

By the time a facility is short a cabling crew or a NOC team, the labor market has already moved. Closing that gap starts on the project plan, not the punch list.

8 min read • September 2026
35 GW
Data center capacity under construction in North America (JLL)
1%
Record-low data center vacancy, 2nd year running (JLL)
349K
Net new construction workers needed in 2026 (ABC)
9.9 mo
Avg. backlog for contractors with data center work, vs. 8.3 mo without (ABC)

Key Takeaways

  • Demand is outpacing labor supply: contractors doing data center work carry longer backlogs than the rest of the industry (9.9 vs. 8.3 months, ABC, Sept. 2026), while vacancy on finished capacity sits at a record-low 1% (JLL, Feb. 2026).
  • Staffing needs are not constant across a project. Cabling and low-voltage crews peak during fit-out; deployment and test technicians peak during systems integration; operations and NOC staff need to be in place before turn-up, not after.
  • Data center trades compete against a construction sector that needs 349,000 net new workers in 2026 alone (ABC, Jan. 2026), so sourcing only once a role is urgent means competing for what is left of an already tight pool.
  • Reactive recruiting collides with construction timelines that have already stretched: delivery windows that used to run 12–18 months now regularly extend into multi-year territory (CBRE, Jan. 2026).
  • Mapping workforce milestones to project milestones, starting at design and pre-construction, is what closes that gap.

North American data center construction has a scale problem and a speed problem at the same time. JLL now tracks 35 GW of capacity under construction, and vacancy for finished space has sat at a record-low 1% for two straight years. Every one of those projects needs cabling crews, integration technicians, and operations staff before it can go live.

Most project plans still treat workforce as a construction-phase problem — something the general contractor or the operator figures out once trades are needed on-site. That works when labor is easy to find. It does not work in a market where contractors doing data center work already carry longer backlogs than the rest of the industry, and where the broader construction sector needs 349,000 net new workers in 2026 alone.

The Timing Problem: Why Workforce Planning Has to Start Before Construction

Construction and delivery timelines for data centers have moved. CBRE's 2026 outlook notes that the traditional 12- to 18-month delivery window for sub-50-MW facilities is no longer representative of the market, and that large AI campuses now run on multi-year construction schedules. Interconnection alone can add 24 to 48 months when utility upgrades are required.

Power and site work get planned against those timelines from day one. Workforce too often does not. A staffing plan that starts once a phase is already underway is, by definition, starting after the point where the most experienced technicians could have been secured.

"A staffing plan that starts once a phase is already underway is starting after the point where the most experienced technicians could have been secured."

The data center sector is not staffing in isolation. It draws from the same skilled trades pool as every other construction project, at a moment when the industry needs to attract 349,000 net new workers in 2026. Waiting to plan staffing until a role is urgent means competing for the same shrinking bench everyone else is also sourcing late for.

Treating workforce planning as a project-planning input — reviewed alongside budget, schedule, and design — rather than a construction-phase task is what keeps a project from finding this out the hard way.

The Lifecycle: How Staffing Needs Shift Across the Data Center Lifecycle

A data center project does not need the same people from groundbreaking to go-live. The mix shifts at every phase, and each shift carries its own lead time.

Shell and core construction calls for the general trades and electrical and mechanical rough-in that any large commercial build needs. Once the building is enclosed, the project moves into infrastructure and fit-out, where structured cabling and low-voltage technicians, fiber splicers, rack and pathway installers, and electrical and controls technicians become the critical path. Cabling and low-voltage work is labor-intensive and easy to under-resource, since it runs in dense pathways and rack spaces where workmanship and labeling standards carry directly into commissioning.

As physical infrastructure comes online, the project shifts into systems integration and testing: deployment technicians racking and stacking IT hardware, network and security technicians handling connectivity and configuration, and test and validation support working under the direction of commissioning teams.

Commissioning and turn-up is the highest-risk transition in the lifecycle, because it is where a project moves from construction mode to live operations. Data center technicians, NOC and monitoring analysts, and on-site support staff need to already be in place — not hired after commissioning wraps — so that knowledge transfer from the build team actually happens instead of being reconstructed from documentation after the fact.

The Labor Market: Competing for Skilled Technical Labor in a Tight Market

Data center projects are not staffing against a stable labor pool. They are staffing against a construction sector that needs 349,000 net new workers in 2026, and against each other: roughly 1 in 6 ABC member contractors now hold data center contracts — the highest share on record — and those contractors carry a 9.9-month project backlog versus 8.3 months for contractors without data center work.

That competition is also spreading geographically. JLL's year-end 2025 report found that 64% of the North American construction pipeline now sits outside the traditional hub markets, as capacity growth pushes into more than 40 frontier markets. Many of those markets do not have the deep bench of experienced structured cabling, low-voltage, and commissioning technicians that hub markets have built up over a decade of data center construction.

Quick Assessment

When does workforce planning enter your data center project timeline?

The answer says a lot about how much schedule risk is already built in.

The result: technical trades specific to data center work — not general construction labor — are the tightest part of the labor pool, and they are getting tighter in exactly the markets where new capacity is being built.

The Cost of Reacting: Why Reactive Recruiting Creates Schedule Risk

Reactive recruiting means sourcing a role once it is already needed on-site, rather than planning for it in advance. In a labor market with the backlog and shortage numbers above, that timing has a direct cost.

CBRE's 2026 outlook and JLL's year-end 2025 report both point to interconnection and grid-connection timelines that now average four years or longer in many markets. When the infrastructure side of a project is planned on a multi-year clock, but staffing decisions are made in the weeks before a phase starts, workforce becomes the variable most likely to slip.

Contractors already carrying a 9.9-month backlog on data center work have little slack left to absorb a late hiring scramble without it showing up in the schedule. A gap in cabling crews during fit-out, or a late start on NOC hiring before turn-up, does not stay contained to that phase — it pushes into the phase after it, because commissioning cannot start until fit-out is verified, and operations cannot take over until commissioning is complete.

Quick Assessment

Who owns the handoff between build crews and operations staff on your projects?

Commissioning and turn-up is where staffing gaps turn into schedule risk.

This is the mechanism behind most of the handoff friction owners and GCs describe on data center projects: not a single dramatic shortage, but a staffing decision made a phase later than the infrastructure timeline required.

The Fix: Building Workforce Milestones Into the Project Plan

The fix is procedural, not exotic. Workforce milestones belong on the same schedule as design, permitting, and construction milestones, mapped to the phases above:

  • Identify which roles are needed for each phase, and in what volume, during design and pre-construction — not once a phase begins.
  • Plan for overlap between phases, so some staff carry knowledge from construction into turn-up and early operations instead of a clean handoff with no continuity.
  • Build in lead time for the technical trades — structured cabling, low-voltage, commissioning support — that are hardest to source on short notice.
  • Engage a specialized staffing partner early enough to align staffing needs with your project phases and schedule, rather than after a gap has already opened.

That last point is where Anistar's role fits. Anistar supplies technical workforce across the data center lifecycle: structured cabling and low-voltage technicians, rack and pathway installers, and electrical and controls technicians for infrastructure and fit-out; deployment, network, and security technicians and test and validation support for systems integration and testing; and data center technicians and NOC or monitoring staff to bridge into turn-up and early operations. Anistar works with project and operations leaders to align that staffing with program schedules and milestones, and handles the sourcing, screening, documentation, and payroll administration behind it, so internal teams stay focused on delivery instead of recruiting logistics. Explore Anistar infrastructure staffing, or connect with our team to map workforce milestones against your project schedule.

Plan the Workforce Before You Plan the Groundbreaking

Anistar supports data center staffing across the full lifecycle — from structured cabling and low-voltage crews through systems integration, commissioning, and early operations.

Explore Infrastructure StaffingRequest Talent
data center workforce planningdata center staffing lifecycledata center construction staffingNOC staffingAnistar

Frequently Asked Questions

Because the technical trades a data center needs — structured cabling, low-voltage, commissioning, and operations staff — sit in one of the tightest parts of the skilled labor market. Contractors already doing data center work carry longer project backlogs than the rest of the industry, and delivery timelines that used to run 12 to 18 months now regularly stretch into multi-year territory. Waiting to staff a phase until it is already underway means sourcing into that same tight market with no lead time.

The skill mix shifts by phase. Shell and core construction needs general trades and electrical/mechanical rough-in. Infrastructure and fit-out needs structured cabling and low-voltage technicians, rack and pathway installers, and electrical/controls technicians. Systems integration and testing needs deployment, network, and security technicians and test/validation support. Commissioning, turn-up, and early operations need data center technicians and NOC or monitoring staff in place before go-live, not hired after.

Schedule slippage. When staffing decisions are made only once a role becomes urgent, projects compete for the same limited pool of experienced technicians as every other data center build on a similar timeline. Contractors already carrying long project backlogs have little slack to absorb a late hiring scramble without it pushing into the next phase.

Owners, developers, general contractors, integrators, and the project leaders responsible for schedule should treat workforce milestones as part of the project plan, alongside design and permitting. Bringing a specialized staffing partner into planning conversations early, rather than after a gap opens, is part of that process.

Anistar supplies technical staffing across construction, fit-out, systems integration, commissioning, and early operations — including structured cabling and low-voltage technicians, rack and pathway installers, deployment and network technicians, and data center/NOC operations staff — and works with project and operations leaders to align that staffing with program schedules rather than treating each request as a one-off.

WORK WITH NSC

Discover the perfect candidates for your organization with our dedicated staffing support team. We're here to connect you with skilled job seekers, tailored to your unique needs. Reach out today, and let us help you build a winning team!

Job seekers, we've got your back too! Explore our extensive job openings and take the next step in your career by going to our jobs page to search and apply today.